A machine does not leave the factory simply because it has been assembled and energised. A set of commissioning actions is carried out during manufacture: the pipework routing and the valve positions are checked through, the wiring and the phase sequence are confirmed, the interlocks between the oil draining, vacuum and heating systems are verified, and the initial settings of the heating and temperature control are fixed. Once these are done in the workshop, the machine on site only needs the pipework connected and the supply switched on before it can enter the normal process.

The TYA-100 documentation states that the no-load and load tests are completed before shipment, with test records and a certificate of conformity supplied with the machine; the ZYD-300 is described as having its pipework, electrical work and interlock commissioning completed at the manufacturing stage, so that the site only has to connect the pipes and switch on the power. Two wordings for the same thing: problems that can be exposed in the workshop are dealt with in the workshop.

What has already been done in the factory

On the pipework, the routing, the fixing, the valve positions and the sealing faces have been checked through, so the state of every connection is traceable once assembly is complete. On the electrical side, the wiring, the phase sequence and the protection settings are done inside the cabinet, and the two chains of phase loss and phase sequence protection and of audible and visual overpressure alarm with shutdown have been operated in the workshop. On the interlocks, the oil draining, vacuum and heating systems are interlocked with each other so that heating without oil and dry burning cannot occur, and the preconditions of temperature in place and vacuum in place are already written into the program. On heating and temperature control, the far-infrared carbon fibre heating and the initial settings of the temperature control are fixed before shipment, and nothing has to be adjusted again on site.

Roots blower and drive motor inside the cabinet of the machine
The way the pump group sits in the cabinet and the way the pipework is routed are fixed and checked before the machine leaves
Completed in the factoryTo be confirmed again on siteWhy it has to be confirmed again
Pipework routing, valve positions and connection sealing checksConnecting on site, joint sealing and the fall of the inlet and outlet linesTo rule out leaks and air locks introduced by the site connections
Wiring and phase sequence confirmationChecking the phase sequence of the site supply, the earthing and the coordination of the protectionTo make sure the preconditions for the protection to operate are in place
Interlock relationships and protection settingsConfirming the response of the interlocks and the alarms on site, one by oneSo that the overpressure, phase loss and foam chains really are available
No-load and load testsThe single machine test run on siteTo confirm that the whole process works after the connections are made

What to watch during the first test run on site

The first test run does not need oil in the machine. Energise it first and look at the indicators and instruments on the cabinet: whether the vacuum gauge and the pressure gauge have returned to around zero, whether the temperature display is normal, whether the audible and visual overpressure alarm works, and whether the emergency stop and the interlocks act as expected. This step confirms that what was adjusted in the workshop still holds on site.

Only after that should oil be admitted, and the order of the earlier steps has to follow the process as well: build the vacuum and bring the heating to the set point before the oil enters the chamber, and set the temperature range as 45–80 °C, with the upper limit pressed down to 70 °C for oil with a high water content. That order is itself part of the interlocking, and following it stops a good many problems before they happen.

What the factory test record should contain

The factory test record in the random documents is the evidence left by those commissioning actions: whether the test was no-load or load, how long it ran, which readings were taken and what the conclusion was. There is no need to repeat the whole experiment to check it; look first at whether the record covers the process steps that matter: whether the vacuum can be built, whether the heating reaches the set temperature, whether the pressure circuit triggers an alarm, and whether the interlocks operate as intended. Where something is missing, watch that item during the first run on site and add the reading to the record.

  • At handover, collect three things: the certificate of conformity with the factory test records, the random documents and the spare parts list.
  • Put the key readings from the factory test record next to the readings from the first test run on site.
  • Any change made on site, such as the length of the pipework, the power supply or the element specification, goes into the machine file.
The plate and frame group and the control cabinet of a plate and frame filter press
Every machine goes through the same commissioning actions before it leaves, and the random documents carry the matching record
What was commissioned in the factory is there to keep the number of problems on site down; the job on site is not to adjust everything again but to confirm that the conclusions reached in the workshop still hold here.