On the day the machine arrives, most attention goes to whether the casing has been knocked, whether the pipework has been distorted and whether the technical documents are all there. What really decides how the machine behaves afterwards is more basic: what the machine is standing on. Confirming this before the machine is placed costs very little; finding it out afterwards is far more expensive to put right, and it often lands right in the middle of a maintenance window.

Load capacity is the one that cannot be compromised

The weight of the ZYD-100 is about 720 kg and the overall dimensions are 1200×1400×1800 mm; the TYA series and the mobile units weigh no less. The result of insufficient load capacity is not a collapse on the spot but a set of continuing problems that appear after the machine has been running for a while: deformation of the frame, uneven contact between the feet and the floor, loose bolts and a pump set that drifts out of alignment.

What has to be confirmed is the total weight of the machine with the working medium filled in, not the weight of the empty machine, and it is the force on the four support points, not an average spread over the whole footprint. A concrete base needs a clear strength requirement, and where that cannot be provided a steel platform with enough capacity is used as a transition. Adding more feet does not solve it, it only pushes the problem into the future.

Levelness decides whether the machine shakes on its own

The effect of levelness is underestimated. If there is a step between the bottom of the frame and the floor, the machine moves and vibrates in a cycle while the pump set runs. The vibration travels along the pipework, the mating faces are loaded repeatedly, and flanges, joints and sealing rings are the first to fail; carried further up the machine, the alignment between the motor and the pump slowly drifts, the current rises and the oil temperature goes up.

A second problem caused by unevenness is the cooling. Where the gap under the machine is not even, the air path is partly blocked and the working temperature of the heating section and the motor moves away from the design state. The overall envelope of 1200×1400×1800 mm leaves little room to work in, so whether the four corners are at the same level has to be measured before installation rather than judged by eye.

The base of the oil purifier and the pipework running along the ground
How the base sits on the floor decides how stable the machine is, and the route the pipework takes along the ground has to be planned at the same time

The typical problems behind the three conditions

Floor conditionTypical problemHow to confirm itPossible consequence
Load capacity insufficientThe feet sink and the frame deformsCheck the base strength against the total weightAlignment drift, loose connections, vibration gets worse
The floor is not levelThe machine rocks in a cycleCheck the level of the four corners with a spirit levelSealing parts fail early, current and oil temperature rise
Oil and dust on the floorThe oil pipework corrodes and the cooling is restrictedClean it and confirm the cleaning routine on siteShorter life of the machine, unplanned stops
Poor drainage and standing waterMoisture in the electrics, insulation fallsCheck the drainage and the fall of the floorLeakage protection trips, faults in the control cabinet
Too close to a source of vibrationVibration from the two adds upKeep a distance from overhead cranes, presses and the likeReadings fluctuate, fasteners work loose

Choosing the measures against vibration

  • Fit vibration pads or spring mounts between the machine base and the structure of the building, so that less vibration is passed on.
  • Fit flexible connections at the inlet and the outlet of the pump set to absorb the vibration and the shock coming along the pipework.
  • Fix the inlet and the outlet pipework with supports, so that it does not hang free and swing over a long run.
  • Keep a distance from the source of vibration and, where that is possible, turn the machine so that the vibration directions do not line up.
  • After installation, run the machine unloaded once and measure the settlement and the vibration at each foot.
  • Put the measurements into the installation file, to serve as the reference for later maintenance.

When these checks should happen

The condition of the floor is part of the installation plan, not a remedy to be found during installation. The form of the base and the loads are settled at the drawing stage, the level and the drainage are checked on site, and the vibration and the current data verify the result once the machine is in service. When all three are done, the later work on the alignment and on the sealing has a stable starting point; leave one of them out and the problem returns six months later in a different form.

The condition of the floor is something that can be confirmed before the machine arrives; finding out afterwards that the floor cannot carry it costs far more to put right.